2.14 Subsurface Utility Engineering (SUE)88/

Practice Statement:

When applied properly during the design phase, Subsurface Utility Engineering (SUE) provides significant cost and damage-avoidance benefits and the opportunity to correct inaccuracies in existing facility records.19

Practice Description:

In certain cases and environments, it may be difficult or impossible to determine the locations of all utilities and/or impediments with sufficient accuracy to avoid damage or delay during construction. In these cases, SUE is applied during the design phase to locate, identify, and characterize all existing utility infrastructure (and other relevant non-utility features) found within a given project/area. SUE is applied in a structured manner in accordance with practices and quality levels found in ASCE 38-02 “Standard Guideline for the Collection and Depiction of Existing Subsurface Utility Data.” The project owner dictates the required quality levels (QL) as well as the amount of effort expended by the SUE provider on each. Although the standard is more detailed and comprehensive, the following is a brief summary of the quality levels defined therein:

  • QL-D involves utility records research and interviews with knowledgeable utility personnel.

  • QL-C involves surface survey and identifying and recording aboveground features of subsurface utilities, such as manholes, valves, and hydrants.

  • QL-B involves application of “surface geophysical methods,” such as EM-based locating instruments, GPR, radar tomography, metal detectors, and optical instruments, to gather and record approximate horizontal (and, in some cases, vertical) positional data.

  • QL-A involves exposure of a facility by safe excavation practices to ascertain the precise horizontal and vertical position of underground lines or facilities.  Accepted safe excavation practices vary by state/local jurisdiction, but the preferred techniques include hand digging with extreme caution and/or vacuum excavation.  (See Best Practice 5-32.)

SUE results are integrated into the design process, in which design engineers use the information to create construction plans that accommodate existing infrastructure, thereby reducing the overall risk of conflicts and/or damage.1

References:

  • U.S. Department of Transportation—FHWA (12/1999). Cost Savings on rojects Utilizing Subsurface Utility Engineering. Pub. No. FHWA-IF-00-014

  • U.S. Department of Transportation—FHWA (3/2001). Subsurface Utility Engineering: Enhancing Construction Activities. Pub. No. FHWA-IF-01-011

  • ASCE 38-02 Standard Guideline for the Collection and Depiction of Existing Subsurface Utility Data

  • Pennsylvania state law

  1.  TR-2004-03: Amendment approved by the CGA Board on March 4, 2005

Submit a Best Practice Proposal

Download a Copy

Purchase a Book

Access Best Practices Toolkit

Damage Prevention in Your State

Explore damage prevention information, local contacts and rules for safe digging in North America.

Find Your State

CGA Toolkits

CGA has created a suite of toolkits designed to help members generate public awareness about the importance of damage prevention.

Explore Resources